Why does Case Builder show Case Tasks as non interconnected boxes? (Choose two)
A. Tasks have a small adornment to the left of the box that indicates the order or execution that takes place after the case has reached the Ready state
B. Case Builder is not used to model the execution order amongst all tasks
C. Tasks are designed to be tools for the case worker
D. Connectivity is not needed because all the tasks start automatically when the case is first created
E. They may be initially disconnected but are eventually connected in the Step Editor
正解:B,C
質問 2:
Which two statements are correct about a design object store? (Choose two)
A. Contains a solution package of each solution
B. Solutions are deployed and tested in the design object store
C. A design object store is not allowed in a production environment
D. Each Case Manager/P8 Domain allows one (and only one) design object store
E. Each Case Manager/P8 Domain allows one or more design object store
正解:A,D
質問 3:
You are getting a "FNRPA0024E IBM Case Manager Builder cannot connect to the Process Engine" error message when logging into the Case Manager Builder page. What Process Engine log files can you check to see if Process Engine is up and running?
A. Check the pesvr_system.log file, which is located in the logs directory under the Process Engine virtual server directory ( Process_Engine_installation_directory/data/pesvr. Process_Engine_virtual_server_name/logs)
B. Check the pesvr.log file, which is located in the Process Engine virtual server directory(Process_Engine_installation_directory/data/pesvr.Process_Engine_virtual_server_name)
C. Check the pe.log file located in the the Process Engine virtual server directory ( Process_Engine_installation_directory/data/pesvr. Process_Engine_virtual_server_name)
D. Check the pe.log file, which is located in the logs directory under the Process Engine virtual server directory (Process_Engine_installation_directory/data/pesvr.Process_Engine_virtual_server_name/logs)
正解:A
質問 4:
Which of the following is NOT a difference between a development and production Case Manager environment?
A. Solutions may be modified in the development environment and should not be modified in the production environment
B. In a development environment there must be a design object store and a target object store, in a production environment only one or more target object stores is required
C. In a development environment, Case Manager Builder is used to deploy solutions. In a production environment, Case Manager Administration Client is used to deploy solutions
D. Production Case Manager environments can take advantage of P8 distributed deployment and domain partitioning configuration options while development cannot
正解:B
質問 5:
Your case management solution requires case workers to have a view of information managed in a system external to IBM Case Manager and P8. How do you integrate such a view into the IBM Case Manager case worker's environment?
A. Use an IBM Forms Widget
B. Integrate a mashup widget that displays the external system information
C. Use the Case Data Widget
D. Extend the Case Information Widget
正解:B
質問 6:
Which statement is correct about a Reset Test Environment?
A. Deletes then re-creates target object store and re-initializes the Process Engine region. It does not change the Design Object store
B. Re-initializes the Target Object Store by removing all case objects. All deployed solutions remain in the Target Object store for continued testing
C. Deletes all solutions in the Design Object Store and deletes then re-creates the Target Object store and re-initializes the Process Engine region
D. Deletes all solutions in the Design Object Store only
正解:A
質問 7:
In the Step Editor tool you can add swimlanes to a task so you can divide the work among roles and workgroups. You can then add one to many steps in the swimlanes. You have Role swim lanes and Workgroup swim lanes. Which two represent the difference between a role and a workgroup? (Choose two)
A. A user may not be assigned to a role and a workgroup at the same time
B. Both roles and workgroups are assigned to Process Engine work queues. Workgroups add an assigned To property that is used to filter the work for a user
C. Roles can be reused for multiple tasks and case types. Workgroups are created at the task level and not shared among other tasks or case types
D. The Process Engine creates a work queue for each role in the solution. Workgroups are not assigned to a work queue. They are assigned to personal In baskets
E. A role can have many users assigned and a workgroup can only have one user assigned
正解:C,D