Click the Exhibit button.

The use case requires that a manager is notified when an activity misses a deadline. If the activity is completed before the manager opens the notification, the notification should be withdrawn from the work list.
Which two configurations must be implemented to satisfy this requirement? (Choose two.)
A. The Timer Event must be configured as Withdraw Task on Timeout
B. The Timer Event must be configured as Continue Task on Timeout,
C. The Throw Signal Event must have a unique Signal Name.
D. The Catch Signal Event must have a unique Signal Name.
正解:B,C
質問 2:
Which three statements are true about Personal or Supervised Work Views? (Choose three.)
A. By default, there are no Work Views in the Supervised Work folder.
B. To supervise work items of other users, you must have the View Work List Scoped system action.
C. Supervised Work Views of an organizational entity can contain Offered and Allocated work items.
D. The Personal Work View can only contain Allocated work items.
E. The Personal Work View can be removed and replaced with a Supervisor Work View.
正解:A,B,C
質問 3:
Which two methods can be used to assign a participant in a User task at design time? (Choose two.)
A. Selecting an Organization Model entity
B. Using a participant expression
C. Using an LDAP reference
D. Using a performer data field or parameter
正解:A,C
質問 4:
Which two statements are true about Scoped system actions? (Choose two.)
A. They are set on the Organization Model.
B. They are set on specific Groups, Organization Units and Positions.
C. They are used to control Supervised Work Views.
D. They are used to control process instances.
正解:B,C
質問 5:
Which requirement must be met by User tasks that are chained together?
A. They must have Offer to One as their distribution strategy.
B. They must be offered to different participants.
C. They must be allocated to different participants.
D. They must have Offer to All as their distribution strategy.
正解:D
質問 6:
Which three statements are true about the relationship between User tasks and forms? (Choose three.)
A. When a form is created from a User task, the parameters need to be manually bound to form controls.
B. The Synchronize Form operation on the form will update the User task parameters to match the form parameters.
C. The Synchronize Form operation on the User task will update the form parameters to match the User task parameters.
D. When a form is created from a User task, the form parameters are automatically set to match those in the User task.
E. A User task and a form have their own separate models for input and output parameters.
F. A User task and a form share the same model for input and output parameters.
正解:C,D,E