During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?
A. Review and update the stakeholder engagement plan
B. Update the risk register.
C. Review and update the detailed stakeholder list
D. Execute the component project's communications management plan
正解:A
質問 2:
Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?
A. Three RU of cable management panel for each RU of patch panel
B. Two RU of cable management panel for each RU of patch panel
C. Two RUs of management panel for each RU of cable patch panel plus two additional RUs of cable management
D. One RU of management panel for each RU of cable patch panel plus one additional RU of cable management
正解:D
質問 3:
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
A. Project manager
B. Communications manager
C. Program manager
D. Program sponsor
正解:C
質問 4:
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?
A. Mitigate the risk before it is incorporated into the risk management plan
B. Document the risk in the program transition plan and identify it as a potential issue
C. Document it m the issue log and immediately notify the steering committee
D. Incorporate it into the risk register and perform a thorough analysis
正解:D
質問 5:
In specifying labels and pruned tags that meet Underwriters Laboratories (UL) 969 Standard, marking and labeling systems are provided following the listed metrics. Which two of the following are REQUIRED for the UL standard? (Select two options.)
A. Thickness test
B. Visual inspection
C. Durability test
D. Texture test
E. Adhesion test
正解:B,E
質問 6:
What would prevent a program manager from completing program closure once a program has been completed?
A. Failure to update the benefits register
B. Incomplete realization of all program benefits
C. Failure to update the financial management plan
D. Failure to obtain program steering committee approval
正解:D
984 お客様のコメント





Takagi -
私は1日4時間を3日で合格できました。(ぎりぎりでしたが……一応合格なので…笑)試験は暗記が勝負のところがあるので、そこは少し手間かもしれません。