Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,
A. Both 1 and 2 are true
B. Neither 1 or 2 are true
C. Only 2 is true
D. Only 1 is true
正解:B
質問 2:
Which is a purpose of the Starting up a Project process?
A. Learn lessons from this project
B. Ensure the communication requirements of all stakeholders are documented
C. Prevent poorly conceived projects from ever being initiated
D. Document how changes required by corporate or programme management will be reviewed
正解:C
質問 3:
Which describes the 'Identify Risks' step within the recommended risk management procedure?
A. Gather information about the project environment and objectives
B. Identify responses to risks documented in the Business Case
C. Identify uncertainties that may impact on the delivery of the project objectives
D. Identify the roles to be involved in risk management activities
正解:C
質問 4:
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
A. Business Case
B. Plans
C. Risk
D. Quality
正解:A
質問 5:
Which of the following statements about the Closing a Project process are true?
1.The Closing a Project process provides a fixed point for the receipt of completed Work
2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
A. Both 1 and 2 are true
B. Neither 1 or 2 are true
C. Only 2 is true
D. Only 1 is true
正解:C