A consultant is onsite and needs to start their Foundation Virtual Machine (FVM) to image Nutanix hardware. The FVM fails to boot. The consultant decides to use a different Foundation method.
Assuming the nodes will discover, which Foundation type or configuration option should the consultant select?
A. Use IPMI IPs
B. Foundation VM
C. Use IPMI MACs
D. Foundation Applet
正解:D
質問 2:
During the Foundation imaging process, nodes are successfully imaged, but the cluster creation fails.
Which log should the consultant review to determine the cause?
A. service.log
B. first_boot.log
C. genesis.out
D. foundation.out
正解:A
質問 3:
For a new AHV cluster installation, a customer has 20 NX-8155-G6 nodes with quad port SFP NICs.
The customer wants to meet the following guidelines:
* Take advantage of all available 10GbE links
* Achieve maximum throughput per VM
* Use of redundant ToR switches
* Fastest reconvergence during link failure
How should the load balancing be configured on the host?
A. ovs-vsctl set port br0-up bond_mode=active-backup
ovs-vsctl set port br0-up other_config:bond-rebalance-interval=30000
B. ovs-vsctl set port br0-up bond_mode=balance-slb
C. ovs-vsctl set port br0-up other_config:lacp-fallback-ab=true
ovs-vsctl set port br0-up lacp=active
ovs-vsctl set port br0-up bond_mode=balance-tcp
D. ovs-vsctl set port br0-up bond_mode=balance-slb
ovs-vsctl set port br0-up other_config:bond-rebalance-interval=30000
ovs-vsctl set port br0 tag=10
正解:D
質問 4:
A consultant needs to review a customer's switch port configuration to identify any issues. Other customer requirements are as follows:
* Leverage LACP
* Native VLAN will not be used
* Use Multiple Upstream switches
* Use VLANs 20-25 and 30
* LACP Fallback has been Enabled
* vPC or MLAG has been configured
What must be included in a configuration in order to meet these requirements?
A. Native VLAN set to default
Ports trucked to allow all necessary VLANs
B. Native VLAN set to 30
Ports in access mode to allow all necessary VLANs
C. Native VLAN set to default
Ports in access mode to allow all necessary VLANs
D. Native VLAN set to 30
Ports Trunked to allow all necessary VLANs
正解:A
質問 5:
A customer wants to know the details of network validation testing.
Where can the consultant find this information?
A. Handover checklist
B. As-Built Guide
C. Operations Guides
D. Test plan
正解:A