You are asked to configure telemetry on the OFX Series devices in your data center fabric. You want to use sensors that have a vendor-neutral data model Which type of sensor should you use in this scenario?
A. JTI OpenConfig sensors
B. JTI native sensors
C. analog sensors
D. Python sensors
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Exhibit.

You have implemented an EVPN-VXLAN data center. Device served must be able to communicate with device server2.
Referring to the exhibit, which two statements are correct? (Choose two.)
A. An IRB interface must be configured on spinel and spine2.
B. Traffic from server! to server2 will transit the VXLAN tunnel between leaf1 and Ieaf2.
C. An IRB Interface must be configured on leaf1 and Ieaf2.
D. Traffic from server1 to server2 will transit a VXLAN tunnel to spinel or spine2. then a VXLAN tunnel from spinel or spine2 to Ieaf2.
正解:B,C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
You are adding a server lo a tenant's network within your data center and must limit access to a specific traffic type within the tenant network without pushing all tenant traffic through a firewall.
What will satisfy this requirement?
A. Use route leaking with EVPN and a routing policy.
B. Put the new server on a unique subnet within the tenant's network.
C. Use filter-based forwarding.
D. Use a static route in the tenant VRF with a firewall as the next hop for traffic to the new server.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Exhibit.

Both DC and DC2 ate using EVPN-VXLAN technology deployed using an ERB architecture. A server on the Red VLAN must communicate with a server on the Green VLAN. The Blue VLAN in DC and DC2 needs to be the same VLAN.
Which statement is correct in this scenario?
A. The eight spine devices must be configured as border spine devices; a full mush interconnect must exist between all eight spine devices and the Blue VLAN must be stitched together
B. A lean super spine device must be added to DC and DC2; all VLANs must be stretched to the lean super spine device and the lean super spine devices must stitch all the VLANs together.
C. An interconnect is required between four leaf devices in the services blocks; the Red VLAN and the Green VLAN must be stitched and the Blue VLAN must be stretched.
D. An interconnect is required between the four SRX Series devices; the Blue VLAN must be stretched and a transit VNI must be added for the Red and Green VLANs.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Exhibit.

You are troubleshooting a DCI connection to another data center The BGP session to the provider is established, but the session to Border-Leaf-2 is not established. Referring to the exhibit, which configuration change should be made to solve the problem?
A. delete protocols bgp group OVERLAY accept-remote-nexthop
B. set protocols bgp group overlay export loopbacks
C. delete protocols bgp group UNDERLAY advertise-external
D. set protocols bgp group PROVIDER export LOOPBACKS
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
Tsuchiya -