Match the correct responsibility with each participant of a second-party audit:

正解:

Explanation:

Explanation:
Prepares the audit report # Audit Team Leader:The Audit Team Leader is responsible for compiling and preparing the final audit report, summarizing findings and conclusions.
Prepares audit checklists for use during the audit # Auditor:Auditors create checklists to ensure a thorough and systematic evaluation during the audit.
Participates under the direction and guidance of an auditor # Auditor in Training:An auditor in training works under supervision to gain experience and contribute to the audit process.
Follows up on audit findings within an agreed timeframe # Auditee:The auditee is responsible for addressing and resolving audit findings and providing evidence of corrective actions.
A person who accompanies the audit team but does not act as an auditor # Observer:Observers are typically external parties or internal personnel who watch the audit process but do not participate actively.
Escorts the auditors but does not participate in the audit # Guide:A guide facilitates the audit by helping auditors navigate the site and access relevant areas or documents.
References
ISO 19011:2018: Guidelines for auditing management systems.
質問 2:
Wokrer ' s participations is a key factor for the success of OHSMS. Which three of the following ISO 45001 activities require workers ' participation?
A. Establishing OHS objectives
B. Determining actions to eliminate hazards
C. Determining what needs to be communciated
D. Determining competence requirements
E. Establishing OHS policy
F. Managing internal audit programme
正解:A,B,E
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
During discussions with the individual(s) managing the audit programme of a certification body, the OHS Manager of the client organisation asks that only one auditor is used for the audit duration to save on travel expenses.
Which two of the following responses should the individual(s) managing the audit programme make?
A. Suggest asking the certification body management to consider the request.
B. Suggest that the OHS Manager chooses another certification body.
C. Advise the OHS Manager that his request can be accepted.
D. Advise that his request will be considered and we will respond accordingly.
E. Advise the OHS Manager that the audit duration and team make-up is decided in line with the internal procedures of the certification body.
F. Suggest asking the accreditation body management to consider the request.
正解:D,E
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Select two options that are corrections.
A. Using OHSMS induction training to address an identified lack OHSMS awareness among winkers.
B. Changing a process to reduce its inherent risk.
C. Updating the emergency preparedness plan as a result of carrying out a practical test.
D. Reviewing workers training records.
E. Changing the name of a tutor that did not deliver a course to the name of the tutor that did.
F. Adding a missing signature to a corrective action record.
正解:E,F
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
" ISO 45001:2018, in clauses 6.1.3 and 9.1.2, refers to " legal requirements and other requirements " . From the list below, select two that are " other requirements " .
Note: ILO stands for " International Labour Organisation "
NGO stands for " non-governmental organisation "
A. Opinions on legal compliance by a customer
B. Instructions on product use by customers
C. Agreements between the organisation and workers
D. Requirements from neighbours
E. ILO initiatives the organisation subscribes to
F. Requirements established by the government
正解:C,E