Before using U2020 remote NR base station commissioning, which of the following tasks must be prepared?
A. Manually configure the IP address of the base station
B. Base station DHCP service is enabled
C. The plug and play function of U2020 is turned on
D. The physical transport network is in place
正解:B,C,D
質問 2:
Which of the following bands is not included in the candidate SUL spectrum for uplink and downlink decoupling in the C-band?
A. 900MHz
B. 2600MHz
C. 700MHz
D. 1800MHz
正解:A
質問 3:
In the inter-station DC scheme, the X2 interface can be used to achieve transmission intercommunication between LTE and NR sites, but how long does the transmission delay take?
A. <30ms
B. <20ms
C. <40ms
D. <10ms
正解:B
質問 4:
5G RAN side service slice management, which of the following facilities is implemented?
A. GUY
B. AAU
C. OF THE
D. WITH
正解:D
質問 5:
What is the maximum output power of AAU5613?
A. 100W
B. 80W
C. 200W
D. 60W
正解:C
質問 6:
How did 4G Lampsite achieve "no point increase" when transforming the NR room into a 3.5Ghz NR room?
A. The number of pRRU antennas becomes 4T4R
B. Increased gain of the pRRU antenna
C. The pRRU transmit power increases
D. The attenuation with fiber is minimal
正解:A,B,C
質問 7:
Which of the following veneers can be occluded?
A. RRU
B. UMPT
C. UPEU
D. UBBP
正解:A,D
質問 8:
Which of the following MML commands are required to add neighbor information across gNodeB?
A. ADD NRCELL RELATION
B. ADD NREXTERINALCELL
C. ADD NRCELL
正解:A,B
Higuchi -