When applying Business Intelligence (also known as data mining) to manage large volumes of construction project data, the source data must
A. first exist in digital format.
B. include advanced algorithms.
C. include outliers and missing data.
D. first exist in hard copy format.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
One word or phrase to describe the process of transitioning from construction to permanent operations by the owner is
A. O&M.
B. move-in.
C. turnover.
D. beneficial occupancy.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which of the following provides details about the front-end activities of the project during the pre-design and design phases, and highlights major project milestones such as substantial and final completion?
A. Baseline Schedule
B. Master Schedule
C. As-Built Schedule
D. Milestone Schedule
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
During the design phase, the CM should perform which of the following tasks?
A. Review plans, final Right-of-Way (ROW) documents, and as-built submittals.
B. Review cost estimate, schematic design, and scheduling conferences with regulatory agencies.
C. Review contract milestones, payment procedures, and communication procedures.
D. Review staffing assignments, labor affidavits, and historical trust.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
A CM is providing support on a $150 million construction project. The agency has a well-developed safety program; however, the contractor is planning to use an innovative, high-risk method for constructing the project. To minimize the owner's risk, the CM should recommend that the owner
A. provide a safety coordinator to perform the necessary project safety functions on behalf of the contractor.
B. modify the CM contract to include safety management to protect the owner's interests.
C. have the contractor submit a safety management plan for review and approval by the owner.
D. ensure they have a contractor-controlled insurance program (CCIP) to cover the safety risk for the project.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor's lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate; and an up-to-date list of any OSHA citations issued to them in the last three years, including the disposition of each citation. This is important because:
A. a contractor with a poor safety record is likely to be a low bidder.
B. contractors only monitor safety if they understand the owner's emphasis on safety.
C. a contractor with a poor safety record may increase the owner's risk and worker compensation costs.
D. extensive documentation is required to demonstrate sufficient due diligence.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?
A. Regulatory agencies
B. CxA
C. Designer
D. CM
正解:D
解説: (Pass4Test メンバーにのみ表示されます)