Your project requires a rush order process in which a delivery document is automatically created immediately after the sales order is saved. In which customizing object do you activate this? Choo the correct answer.
A. Sales document type
B. Sales item category
C. Schedule line category
D. Copy control
正解:A
質問 2:
Your project requires confirmation of sales order quantities for certain materials even if the stock of those materials is currently below the safe y stock level. Where do you configure this? Choose the correct answer.
A. The Item Category group in the material master
B. The scope of the availability check
C. The Special Stock indicator in the Item category
D. The Checking rule at transaction level
正解:B
質問 3:
How do you establish the interface between SAP S/4HANA Sales and Finance? Choose the correct answer.
A. Assign a sales organization to a company code.
B. Uniquely assign a distribution channel to a company code.
C. Set up the upload of the billing document request
D. Set up the general billing interface.
正解:D
質問 4:
Which master data can you use for automatic determination of the delivering plant in a sales order? Choose Three correct answers.
A. Ship-to party
B. Material master
C. Customer hierarchy
D. Sold-to party
E. Customer material info record
正解:A,B,E
質問 5:
A customer orders five different materials. Because these materials are available at different dates and times, the customer agrees to partial deliveries where necessary. However, they want to minimize the number of partial deliveries. What should you do to enable partial deliveries for the order, while ensuring as few deliveries as possible? Choose the correct answer.
A. Set multiple part al deliveries to be allowed for each order item.
B. Set complete delivery required for each order item.
C. Set complete delivery required in the order header.
D. Set the delivery block until all items are fully confirmed.
正解:A
質問 6:
To which combination of organizational units do you assign a warehouse number? Choose the correct answer.
A. Plant and storage location
B. Plant and material staging area
C. Plant and storage section
D. Plant and storage type
正解:A