COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?
A. Easy cost planning
B. Availability control
C. Results analysis
D. Cost forecast
正解:B
質問 2:
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.
A. Internal orders
B. Reservations
C. Sales order items
D. Purchase order items
正解:B,D
質問 3:
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
A. The factory calendar in the work center used for the internal processing activity
B. An activated Scheduling indicator in the control key of the internal processing activity
C. Whether the work for the internal activity is greater than its duration
D. The relationships between activity elements
E. The unit (for example, hour, day) of the field Normal Duration field of the activity
正解:A,B,E
質問 4:
You have saved a network and activates with assigned material components. As soon as you release the network,
you receive the error message "Business transaction cannot be carried out" What could be the reason for this error message?
A. Missing budget for material components
B. Missing reservations for material components
C. Missing authorizations to release material components
D. Missing material availability
正解:D
質問 5:
Which object is used to allocate the costs from a claim to the project structure?
A. Claim
B. Network activity
C. Internal order
D. WBS element
正解:B
質問 6:
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
A. Backward
B. Forward
C. Current date
D. Only capacity requirements
正解:A