A system is designed to accept values of examination marks as follows:
Fail: 0-39 inclusive
Pass: 40-59 inclusive
Merit: 60-79 inclusive
Distinction: 80-100 inclusive
In which of the following sets of values are all values in different equivalence partitions?
A. 0, 45, 79, 87
B. 25, 40, 60, 75
C. 35, 40, 59, 69
D. 25, 39, 60, 81
正解:A
質問 2:
During the software development process, at what point can the test process start?
A. When the design is complete.
B. When the software requirements have been approved.
C. When the code is complete.
D. When the first code module is ready for unit testing
正解:B
質問 3:
Which test management control option is most appropriate to adopt under these circumstances? 2 credits
A. Advise the user community regarding the reduced scope of requirements and the additional incremental delivery.
B. Arrange a meeting with the user community representatives to discuss the user interface.
C. Introduce mandatory evening and weekend working to retrieve the 3 week slippage.
D. Reconsider the exit criteria and review the test plan in the context of the current situation.
正解:D
質問 4:
Which of the following is least likely to be used as a technique to identify project and product risks? 1 credit
A. Brainstorming
B. Expert interviews
C. Independent assessments
D. Inspections
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Given the following figures for the testing on a project, and assuming the failure rate for initial tests remains constant and that all retests pass, what number of tests remain to be run? 3 credits
A. 720
B. 570
C. 700
D. 784
正解:A
質問 6:
Which of the following options describe the causal chain in the correct sequence?
A. Failure, bug, error
B. Error, fault, failure
C. Fault, bug, mistake
D. Mistake, failure, fault
正解:B
質問 7:
A test case starts at S1 and triggers 4 events in sequence: E1, E4, E5, E7. What will be the finishing state and the output(s) from the test case? [K3] Refer to the exhibit
A. S2 and O2
B. S2 and O4
C. S4 and O4
D. S4 and O2
正解:A
質問 8:
You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the following topics should NOT be included in the test progress report? 1 credit
A. Detailed overview of the risk-based test approach being used to ensure the exit criteria to be achieved
B. Status compared against the started exit criteria
C. Recommendations for taking controlling actions
D. Product risks which have been mitigated and those which are outstanding.
正解:A
質問 9:
Which of the following is true of iterative development?
A. It involves the users in the testing throughout.
B. Changes to the system do not need to be formally recorded.
C. It is not suitable for developing websites.
D. It uses fully defined specifications from the start.
正解:A