A company most likely would implement a supplier certification program to:
A. abide by ISO standards.
B. improve the supplier's procurement process.
C. validate the supplier's compliance with requirements.
D. implement point-of-sale (POS) terminals.
正解:C
質問 2:
In the analysis of costs, fixed costs are those that are:
A. constant through the useful life of the asset.
B. independent of the volume of output.
C. inversely proportionate to the volume of output.
D. dependent on the utilization of the asset.
正解:A
質問 3:
A company that has consistently achieved a high level of on-time delivery performance has decided to reduce its inventory level significantly. Which of the following outcomes is the most likely effect of that decision on the company's on time delivery performance?
A. There will be no effect.
B. It will decline until sales erode.
C. It will improve and then stabilize at a higher level.
D. It will decline and then stabilize at a lower level.
正解:D
質問 4:
In large supply chain transformation efforts, companies often ignore which critical component of change?
A. Customers
B. Suppliers
C. Culture
D. Technology
正解:C
質問 5:
A supplier is offering a price discount if more is ordered at one time. The offer should be analyzed to determine if a larger order is appropriate considering: the impact of the
A. increase in average inventory levels on ABC designations.
B. the increase in transportation costs compared to the reduction in ordering cost.
C. the impact of additional items on indirect costs,
D. the reduction in material cost compared to the impact on total holding costs.
正解:A
質問 6:
Which of the following elements of total quality management (TQM) results in a lower overall cost of the product?
A. Compliance to regulations
B. Prevention of failures
C. Speed to deliver
D. Aesthetics of the product
正解:B