In a fixed price contract the:
A. Contractor is paid for actual costs
B. Contactor assumes all the performance risk
C. Contractor has no risk in the project
D. Owner has all the risk
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Resource planning must take all of the following into account except:
A. Earned value techniques established for the project
B. Time available to complete the project
C. Cash flow (expenditures) limitations for completing work on the project
D. Types of materials, equipment and labor skills required to complete the project
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.
The monthly fixed costs are:
Rant-$1,500
Wages - $4.000
Miscellaneous fixed expenses - $500
If there is an additional variable cost of $0.02 per unit, the monthly break even units are:
A. 40,000 units
B. 60,000 units
C. 48,500 units
D. 75,000 units
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.
A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.
What is a method for figuring estimate at completion (EAC)?
A. ACWP + (BAC - BCWP)
B. BCWS + (BAG -ACWP)
C. ACWP + (BAC - BCWS)
D. BCWP + (BAG - ACWP)
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?
A. 10,586
B. 9,280
C. 10,278
D. 9,559
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
The measure of number of units completed divided by work-hours consumed is referred to as:
A. lined value
B. Productivity
C. Cost performance Index (CPI)
D. Credit work-hours
正解:B
解説: (Pass4Test メンバーにのみ表示されます)