Which two statements are true about Groups and Teams? (Choose two.)
A. Objects can be shared with either a Group or a Team.
B. A Team can be assigned to a task, but a Group cannot be assigned to a task.
C. Work requests can be routed to either a Group or a Team.
D. A Group can be assigned to a task, but a Team cannot be assigned to a task.
正解:B,C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Refer to the exhibit.

What do the connector lines between tasks in a Gantt chart represent?
A. Multiple assignments
B. Critical path
C. Predecessor relationship
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
What are two ways to associate milestone steps to tasks? (Choose two.)
A. In the settings area of a task
B. From the Milestone View in the Projects area
C. In-line editing a task list on a project
D. Through bulk-editing multiple tasks
正解:B,C
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
A statement of work is uploaded to the document section of a project as reference material. How should the file be uploaded into Workfront?
A. Proof
B. Approval
C. Document
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Given this information regarding a Task:
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?
A. At Risk
B. Behind
C. On Time
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
What are two characteristics of a Group in Workfront? (Choose two.)
A. A Group assignment is not required for a user.
B. A Group can be tagged in an Update thread communication.
C. A Group can be associated with a Company or a Project.
D. A user can be assigned as Group Administrator of a Group.
正解:C,D
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
What parent object can have child objects?
A. Issue
B. Project
C. Portfolio
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
A. As Late As Possible
B. Must Start On
C. Start No Later Than
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
1294 お客様のコメント





Matsuda -
いやー本当にすげーわ。この問題集を購入したんだけど、三日前にAD0-E903の試験に受けて、試験にある内容はほぼ問題集に出てて凄かった。合格しました。Adobeさん、今後もお世話になります!