Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?
A. Update the project baseline.
B. Recalculate the project timeline.
C. Update the project status.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.
What action should the task owner take?
A. Set the task condition to At Risk.
B. Update the Commit Date on the task.
C. Work on the task and complete it in the given duration.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Refer to the exhibit.

Identified in red on a Gantt chart, what are the tasks called whose changes may affect the overall timeline of a project?
A. Critical Path
B. Milestones
C. Baselines
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?
A. Status
B. Condition
C. Progress Status
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?
A. Visit the Reports page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month."
B. Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select "month of year."
C. Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month of year."
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.
How should the project manager keep these team members apprised of updates?
A. Ask the team members to add the request to their favorites.
B. Subscribe the team members to the request.
C. Make the team members all primary contacts on the request.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?
A. There are incomplete approval workflows on one or more tasks. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.
B. There are incomplete issue predecessors that need to be resolved. The Project Owner can navigate to the project issues section in the left navigation pane to see the incomplete items.
C. The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)