A system administrator is configuring new resources in a new VMware Cloud Director instance.
Which new resources can be created in VMware Cloud Director?
A. Provider Virtual Data Center, vSphere Cluster, Organization, and vApp Template.
B. Storage Policies, Content Library, vSphere Port Group, and VM Template
C. Provider Virtual Data Center, Organization Virtual Data Center, External Network, and Network Pool
D. Site Association, SAML Identity Provider, vSphere Lookup Service, and Custom Roles.
正解:C
質問 2:
Which allocation model can only be non-elastic?
A. Reservation Pool
B. Allocation Pool
C. Flex
D. Pay-As-You-Go
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
An administrator is planning a new VMware Cloud Director deployment and is concerned about secure communications between the clients and servers.
Which two recommended steps would ensure secure communications between the clients and servers? (Choose two.)
A. Create a single certificate for each member of the server group, and import the certificates into the host keystores.
B. Create two certificates for the server group, and import the certificates into each cell's keystore.
C. Create or use an existing wildcard certificate, and import it into each cell's keystore.
D. Create a single certificate and upload it through the Service Provider Portal to all members of the server group.
E. VMware Cloud Director automatically creates self-signed certificates.
正解:B,C
質問 4:
Which plugin, in addition to the VMware vRealize Orchestrator Plugin for Cloud Director, can be used to enable the system administrator to automate tasks in VMware Cloud Director through vRealize Orchestrator?
A. VAPI Plugin
B. SNMP Plugin
C. REST Plugin
D. SOAP Plugin
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which two steps are mandatory before upgrading VMware Cloud Director appliances from 10.1 to 10.2? (Choose two.)
A. Change the database failover from Manual to Automatic.
B. Take a snapshot of the standby VCD appliance.
C. Take a snapshot of the entire VCD appliances cluster.
D. Take a snapshot of the primary VCD appliance.
E. Change the database failover from Automatic to Manual.
正解:D,E
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
The runtime lease of a virtual machine is about to expire. The administrator would like to extend the lease time.
Which action should be taken to complete this task?
A. Renew the VM lease only after renewing the vApp lease.
B. Renew the lease from the vApp action menu.
C. Use the /api/renewlease endpoint to define a new lease time.
D. Extend the storage lease, and runtime will automatically be extended.
正解:B
1049 お客様のコメント





阪田** -
試験の全範囲を網羅するオリジナル問題集です。
問題も解説も良質なので、たくさん問題を解いておきたい方にはおすすめできますね。
しかも試験の問題にも入ていて、高得点で受かりました。