Danger Incorporated is estimating the costs for a new project called the Ninja Project using an algorithm based on the project's scope, duration, and complexity. What type of cost estimate is being used?
A. expert judgement
B. parametric
C. analogous
D. bottom-up
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Joanne is preparing a contract for the construction of a large shopping center.
The project includes 52 retail units, several restaurants, and a parking facility.
Joanne's company has contracted Construct Ltd under a Turnkey project.
She is using a Gantt chart as a schedule in the contract.
Q: What type of payment mechanism is being used in this contract?
Answer Options:
A. Bill of Quantity
B. Cost Reimbursable
C. Activity Schedule
D. Fixed Lump Sum
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which culture type is task-oriented, structured, and uses logic for decisions?
Answer Options:
A. Linear-Active
B. Proactive
C. Reactive
D. Multi-Active
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Skipped
Which of the following describes tacit knowledge? Select all that apply.
A. It can be captured from reports and data
B. It is usually unwritten
C. It is easy to transfer from one person to another
D. It is easy to capture and write down
E. It can be found in Standard Operating Procedures within the procurement department
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which of the following statements about liquidated damages are TRUE? Select all that apply
A. specific performance is a type of liquidated damage
B. the figure must be a genuine estimate of the loss
C. liquidated damages can be claimed when a warranty is breached
D. a set figure is decided in advance
E. the party seeking damages must prove the actual loss in the event of a claim
正解:B,C,D
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Which of the following processes for managing change is the most passive?
A. education
B. coercion
C. persuasion
D. bribery
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Which of the following is true about Engineering, Procurement, and Construction (EPC) Contracts? (Select all that apply.) EPC contracts, commonly referred to as Turnkey Projects, are widely used in construction and infrastructure projects. These contracts require the contractor to design, procure materials, and construct the project to deliver a complete and operational facility to the client.
Answer Options:
A. These contracts are commonly known as Turnkey Projects
B. These contracts are used when forming a partnership between a private and public organization
C. The contractor may operate the building for a certain period after completion
D. The contractor is responsible for the design aspect of the construction
E. These contracts are sometimes referred to as Design and Build Contracts
正解:A,D,E
解説: (Pass4Test メンバーにのみ表示されます)