A customer wants you to explain the results of the preliminary costing of a production order. How are the results determined?
A. The standard cost estimate is copied from the material master and adjusted by the order quantity.
B. The actual quantities are valuated with plan values.
C. The costs are determined by the cost estimate of the reference order.
D. The quantity structure in the production order is valuated by the costing variant settings.
正解:D
質問 2:
What is the name of the infrastructure that supports core business solutions in four subcomponents including people integration, information integration, process integration, and application platform?
A. SAP Business Process Management
B. SAP Web AS
C. SAP Exchange Infrastructure
D. SAP NetWeaver
正解:D
質問 3:
In which master record can you enter a profit center directly? Note: There are 3 correct answers to this question.
A. Cost element
B. Material master
C. Activity type
D. Internal order
E. Cost center
正解:B,D,E
質問 4:
Which data do you need to set up an accrual calculation with the percentage method? Note: There are 2 correct answers to this question.
A. Cost center or internal order (order category 2) as credit object.
B. Accrual settlement rules with percentage method.
C. Accrual allocation cycle with sender receiver segments.
D. Secondary cost element (category 31) as accrual cost element.
E. Primary cost element (category 3) as accrual cost element.
正解:A,E
質問 5:
A customer is using sales order controlling. How are the revenues and cost of goods sold transferred to CO-PA?
A. By settlement.
B. By billing.
C. By outbound delivery.
D. By results analysis.
正解:A
質問 6:
Which of the following do you define in a library of the Report Painter?
A. Characteristics and key figures.
B. Report groups and reports.
C. Formats and format figures.
D. Predefined columns and rows.
正解:A
質問 7:
What are the prerequisites to calculate overhead costs on an internal order? Note: There are 2 correct answers to this question.
A. Assign the costing sheet to the costing variant.
B. Define an overhead key.
C. Define a costing sheet.
D. Assign the costing sheet in the order master data.
正解:C,D