Which statement about the 'directing a project' process is CORRECT?
A. As a minimum, the project board should receive oral reports from the project manager
B. The project board should attend the delivery team's daily stand up meeting
C. The project board may pull reports from the information radiator
D. The project board should receive regular reports focusing on cost and time overruns
正解:C
質問 2:
What is typically added to a user story as the understanding of the requirement evolves?
A. Effort actually expended
B. Definition of 'ready'
C. An epic
D. Acceptance criteria
正解:D
質問 3:
Which statement describes the Kanban approach?
A. It is an iterative timeboxed approach that helps teams generate value
B. It was originally focused in creating new companies and is now used to speed up product delivery
C. It is used to make system improvements using visualization and by controlling work in progress
D. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
正解:C
質問 4:
Which statement is CORRECT with respect to the management of risk using PRINCE2 Agile?
A. It should always be addressed during the daily stand-ups
B. It should always be carried out formally
C. It should always be appropriate to the needs of the project
D. It should always be carried out informally
正解:C
質問 5:
Which two statements about tailoring the business case in an agile environment are CORRECT?
1. It should be unnecessary because products of the highest value will be delivered first.
2. It should identify the minimum viable product and when it will be delivered.
3. It should take into account that the scope may be reduced during the course of the project.
4. It should show the features, the order in which they will be delivered and any dependencies.
A. 3 and 4
B. 1 and 2
C. 2 and 3
D. 1 and 4
正解:C
質問 6:
Which is a purpose of the 'controlling stage' process?
A. To draft the plan for the next stage's work
B. To report stage progress to the project board
C. To establish whether the project is complete
D. To execute and deliver the project product
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
During which process should release planning be done for the FIRST time?
A. Managing a stage boundary
B. Initiating a project
C. Controlling a stage
D. Managing product delivery
正解:A
質問 8:
Which statement about quality tolerances for a product is CORRECT in an agile context?
A. Quality tolerances should be the same for all quality criteria
B. All quality criteria should have zero tolerance
C. Setting quality tolerance relies on prioritising quality criteria
D. All quality criteria tolerance must be fixed
正解:C