Which term best describes an Agile project's approach to risk analysis?
A. Regression
B. Qualitative
C. Pareto
D. Monte Carlo
正解:D
質問 2:
An organization adopts Agile practices and implements an incremental delivery strategy.If implemented correctly, the company should recognize improved:
A. project Return on Investment (ROI) by releasing individual features to market.
B. project cost management by making incremental payments on contracts.
C. customer satisfaction by specifying project shipping dates in the contract.
D. procurement processes by requiring vendors to ship materials as needed.
正解:A
質問 3:
Applying the Pareto rule when prioritizing the Product Backlog means that:
A. more recent requests are usually more important to the business.
B. a small percentage of the work will provide a large percentage of the value.
C. features that are lower priority are more likely to slip to the next iteration.
D. the value of a feature is not realized until the feature is complete.
正解:B
質問 4:
The team estimation game method mainly consists of a:
A. Spreadsheet with backlog issues to be prioritized and each to be given a prioritizationnumber.
B. Pile of cards with user, capability, and value to be prioritized by the project team.
C. Brainstorm session where resources are related to prioritized work packages.
D. White board session where iterations are estimated and related to the project road map.
正解:B
質問 5:
In reference to Scrum, each sprint should produce:
A. Aset of documented product requirements and specifications.
B. Arelease with testable and measurable functionality.
C. An increment of potentially shippable product functionality.
D. An increment of potentially testable product functionality.
正解:C
質問 6:
Retrospectives provide an opportunity for the team to:
A. Understand from the management if the project is achieving the Scope, Quality, Cost, and Schedule goals.
B. Reflect at the end of every iteration and identify improvements that will increase the quality of the product.
C. Set goals at the beginning of the iteration and identify requirements that can be delivered in that iteration.
D. Participate in a mandatory meeting to share status updates across the team and to ensure that everyone is on track.
正解:B