A service contract is going to be expired, which data source is good to create specifications for ITT?
1. Incumbent supplier
2. Maintenance services
3. Alternative supplier
4. User's knowledge
A. 1, 2 and 3
B. 2, 3 and 4
C. 1, 2 and 4
D. 1, 3 and 4
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A school has a contract for the supply of fruit for break time. The school needs the fruit delivered by 10am every morning to be served at 10:30am. How would this best be covered in a commercial agreement?
A. Contractual term
B. Sales of Goods Act 1974
C. Pricing schedule
D. Note on each purchase order
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Maximum Score: 1
An urgent component requirement needs to be purchased to meet the timescales of a project. A supplier proposes using its standard terms and conditions. What risk to the buying organisation could this bring?
A. A breach of competition laws
B. Contract conditions that are favourable to the supplier
C. A breach of the supplier's internal financial controls
D. Contract conditions that are favourable to the buyer
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Maximum Score: 1
Buyer O has placed an order for the supply and installation of six new servers for a total amount of £600,000 from Supplier A. Which of the following could potentially be treated as examples of a liquidated damages clause within the contract for the supply of the servers?
* If the supplier delivers any of the servers late, £1,000 per server will be deducted from the order per day
* This contract is subject to delay remedies of £X - the amount to be agreed by both parties during delivery
* The sum for breach of the completion date for the order is £40,000 per day up to a maximum of 50% of the contract price
* If the performance of any of the servers degrades within five years, a full refund of £600,000 will be provided
A. 1 and 3 only
B. 3 and 4 only
C. 2 and 4 only
D. 1 and 2 only
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which of the following key performance indicators are most likely to use numerical data as the main source of information?
The critical evaluation of project deliverables
The subjective responses of a satisfaction survey regarding a service
The instances of late deliveries within a given month
The occurrence of accidents and near misses in a year
A. 1 and 3 only
B. 3 and 4 only
C. 2 and 4 only
D. 1 and 2 only
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Which of the following is a disadvantage of using input specifications?
A. There is no limit to the number of suppliers who can quote
B. It is difficult to assess suitability of each quotation
C. There is less opportunity for innovation
D. It requires a more proactive approach to monitoring
正解:C
解説: (Pass4Test メンバーにのみ表示されます)