What can be detected by the optional battery inspection instrument? (Multiple choice)
A. Voltage
B. Battery case temperature
C. Frequency
D. Internal resistance
正解:A,B,D
質問 2:
After the UPS5000-E system is installed, which of the following items need to be checked? (Multiple choice)
A. if the ground connection is reliable
B. if the cable layout considers other system wiring in the future.
C. The positive and negative terminals of the battery are wired correctly.
D. if US and battery system mechanical installation is firm and stable
正解:A,B,C,D
質問 3:
When the NetCol5000-A indoor unit and the outdoor unit are not installed separately, the refrigerant line is ().
A. Refrigerant
B. Nitrogen
C. Oxygen
D. Air
正解:B
質問 4:
When the battery is discharged, the discharge voltage of a faulty battery drops rapidly, resulting in insufficient backup time for the entire battery. What should be done?
A. No need to deal with
B. scrapping the entire battery
C. Performing a discharge
D. Forced equalization, replacement of faulty battery
正解:D
質問 5:
If the ECC800 is configured with a SIM card, the SIM card should be installed in ().
A. Below the ECC800 antenna port
B. ECC800 main control module left slot
C. USB interface
D. ECC800 power module slot
正解:B
質問 6:
When the NetCol5000-C commissions the drainage device, lift the high floater by hand for 5 seconds. At this time, the dual water pump is turned on at the same time, and the "discharge abnormality alarm" appears.
A. TRUE
B. FALSE
正解:A
質問 7:
The functions provided by Huawei's monitoring system NetEco are: (multiple choice)
A. Support system power distribution view display
B. Provide a view creation tool for quick configuration view
C. Provide 2D, 3D data center view display
D. Support modular level/cabinet level view display
正解:A,B,C,D