How might test monitoring and reporting differ for a project using a SCRUM development model rather than a V-model?
A. A move to milestone-based reporting, with optional automated dashboards
B. Monitoring is more informal with less need for regular status reports
C. Responsibility for test monitoring and reporting lies with the Product Owner, rather than the test manager
D. Reports are produced on a continuous basis with real-time dashboards and daily status updates
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
What test process is included as part of TPI Next?
A. Identify test environment
B. Identify test execution
C. Identify test specification
D. Identify test conditions
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which test process improvement model consists of five maturity levels?
A. TMMi
B. GQM
C. TPI NEXT
D. CMMi
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
You are Test Manager of a project delivering a workflow system for complex business processes It has been decided a tool is required to increase the efficiency of test execution. What would be a valid issue to consider when deciding whether to build a custom made tool?
SELECT ONE OPTION
A. It may not be possible to integrate the tool with existing tools used in the organisation.
B. The tool may only be useable for this project and have no long term benefits
C. The tool may not meet the specific requirements for testing this project.
D. The tool may be dependent on the person creating the tool if it is not adequately documented.
正解:A
質問 5:
Club 65 to 90 is a holiday club for retired people run by a small company, the IT department consists of 1 Designer, 3 Developers and 1 System Tester Their booking system has been "live" for a number of years and the company has a loyal client base. A variety of automation tools are used for development and testing to improve effectiveness and efficiency.
A new project will introduce a loyalty scheme and both a Business Requirement Specification and a System Design Specification have been produced A Rapid Application Development (RAD) lifecycle model will be used where time is crucial. In the past there have been problems with updates to the existing system, which has affected existing functionality. Testers have not used representative and realistic operational profiles and data, which has led to significant production problems. The following test policy statements have been proposed for the project:
a. Testing must be risk based;
b. A Master Test Plan, confirming to IEEE829, must be produced for each test project; c. Test procedures must be run by a tester who did not write the procedure; d. Regression testing should be carried out on all releases; e. The testers are accountable for all defects found in production; f. Time must be given to designing test environments so that they are representative of the live environment.
Which of the following options identifies the three policy statements that would be MOST beneficial for this project?
A. a. b and e.
B. b. c and f.
C. a, d and e.
D. a. d and f.
正解:D