(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer's Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)
A. Violence is an Employer's Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.
B. The Contractor should have foreseen such risks due to the region's history; therefore, Clause 19 is not applicable.
C. This is an Employer's Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.
D. The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Which of the following obligations are relevant to the Engineer ' s roles with regards to insurance? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
A. The Engineer is entitled to take out an insurance on behalf of the Contractor, in case the Contractor fails to extend the validity of a specific insurance.
B. The Engineer shall receive a copy of the evidence(s) demonstrating Contractor ' s payment of the necessary insurance premiums.
C. The Engineer shall immediately suspend all construction activities at the Site, in case the Contractor failed to take out any necessary insurance.
D. The Engineer should continuously monitor that the Contractor ' s insurance policies are kept valid, and extensions are duly arranged, when necessary.
正解:B,D
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
(Which two statements are correct for the FIDIC Red Book (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
A. Contract Data is part of General Conditions of Contract.
B. The Contract includes the General Conditions and Particular Conditions, and no other documentation.
C. Contract Agreement, Letter of Acceptance and Letter of Tender are part of the Contract.
D. Conditions of Contract means these General Conditions as amended by Particular Conditions.
正解:C,D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
A. The Contractor provides plant and designs (except as otherwise specified) and executes the other works, all in accordance with the Contract, which includes its Proposal and the Employer ' s Requirements.
B. A disproportionate amount of risks is allocated to the Contractor under the General Conditions.
C. The General Conditions allocate the risks between the parties on a fair and equitable basis.
D. The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
A. If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub- Clause 21.4 to obtain a DAAB decision on it.
B. Both ' Disagreement ' and ' Dispute ' are defined terms under the Conditions of Contract.
C. In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.
D. The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.
正解:A,C
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
Which two statements are correct regarding the FIDIC Red Book (edition 2017)?
A. In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.
B. There is never a difference in effect whether in the Particular Conditions when the term " Works " is used, or when the term " works " is used.
C. Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.
D. Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.
正解:A,D