If the Product Backlog is not ready for Sprint Planning, what happens? (Choose the best answer)
A. Identify enough work for the first day and set up a second Sprint Planning meeting when the Product Owner is ready
B. Cancel the Sprint until backlog is ready
C. Work during Sprint Planning to refine the backlog for one Sprint
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
A Product Owner is entitled to postpone the start of a new Sprint after the conclusion of a previous Sprint for the following reason: (Choose the best answer)
A. The Product Owner has not identified a Sprint Goal.
B. Not enough Product Backlog items are "Ready".
C. The QA department needs more time to make the previous Increment "Done".
D. There is no acceptable reason. A new Sprint starts immediately after the conclusion of the previous Sprint.
E. The stakeholders are not happy with the value produced in the previous Sprint.
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
Which is NOT a Scrum role? (Choose the best answer)
A. Product Owner
B. Developers
C. Scrum Master
D. Project Manager
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
When a Developers determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer)
A. The Developers.
B. The Product Owner and the Developers.
C. The Scrum Master, project manager, and Developers.
D. The Product Owner and all stakeholders.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
What are the purposes of the Definition of "Done"? (Choose the best two answers)
A. Help ensure the Increment is releasable
B. Document the Sprint Goal
C. Provide transparency
D. Ensure unit testing occurs
正解:A,C
解説: (Pass4Test メンバーにのみ表示されます)
質問 6:
How much work must the Developers do to a Product Backlog item it selects for a Sprint? (Choose the best answer)
A. A proportional amount of time on analysis, design, programming, testing, and documentation.
B. All development work and at least some testing.
C. As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the Definition of "Done".
D. As much as it can fit into the Sprint. Any remaining work will be transferred to a subsequent Sprint.
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 7:
Must the Product Owner be present at the Sprint Retrospective? (Choose the best answer)
A. It is mandatory. The Sprint Retrospective is an opportunity for the Scrum Team to assess its performance and improve itself.
B. It is not allowed. The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself.
C. It is optional. Attendance is only required when the Product Owner gets invited by the Scrum Master.
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 8:
There are five teams working on a product. How many Product Owners would there be? (Choose the best answer)
A. Let the team decide
B. 5
C. 1
D. It depends
正解:C
解説: (Pass4Test メンバーにのみ表示されます)