Project structure.
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?
A. You can use only numbers for a project coding mask definition.
B. You can use an indicator to determine that only coded project numbers may be used within the project system.
C. The standard project definition must differ from the definition of the operative project.
D. You can create project coding mask X... event if there are project numbers beginning with X.
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 2:
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
A. Investment profile.
B. Costing Sheet
C. Results analysis key
D. Settlement rules
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 3:
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
A. The table of MRP controllers
B. The scheduling parameters for the network
C. The network profile
D. The control key
正解:B
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
A. Backward
B. Forward
C. Current date
D. Only capacity requirements
正解:A
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
A. management in the project definition. Enter the budget in the master data of the top WBS element.
B. Activate availability control For projects in the control area. Enter the plan data for each WBS element.
C. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
D. Activate commitment
E. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
正解:E