You are creating a planning view in the SAP IBP for Microsoft Excel add-in. Which settings can you maintain as default values?
There are 2 correct answers to this question.
Response:
A. Default Display Time (Zone)
B. Default Planning Area
C. Language
D. Permission filter
正解:B,C
質問 2:
Which of the following are functions of the Snapshot Key Figures feature?
There are 3 correct answers to this question.
Response:
A. The most recent snapshot is numbered with the highest number
B. A snapshot takes a copy of a key figure at a particular point in time
C. You can create up to nine time snapshots at periodic intervals, producing a time-lapsed view of your data
D. A snapshot is taken only if a snapshot operator is run
E. Not exposed to the user in planning views
正解:B,C,D
質問 3:
You are creating a Handling resource. What Resource Type do you need to specify?
Please choose the correct answer.
Response:
A. 0
B. 4
C. 1
D. 2
正解:D
質問 4:
You are working with Inventory Optimization Process and you want to use a What If analysis. What parameters are assessed by this analysis?
There are 2 correct answers to this question.
Response:
A. Service levels
B. Changed variability
C. Capacity consumption
D. Number of planning combinations
正解:A,B
質問 5:
Which supply chain challenge is addressed by SAP IBP Demand?
Please choose the correct answer.
Response:
A. Inability to understand and shape actual demand
B. Inability to respond to short term changes in supply and demand
C. Inability to synchronize supply and demand
D. Inability to arrive consensus demand
正解:D
質問 6:
Which of the following conditions are relevant for subtotals in planning view?
There are 2 correct answers to this question.
Response:
A. Only attribute-based totals can be added.
B. The values of the attribute-based total at the highest attribute level in the planning level can be changed.
C. Total value can be added before or after the selected attribute.
D. Total number of attributes that can use subtotals in the planning view can be restricted.
正解:C,D
質問 7:
You create an S&OP operator for heuristics on an SAP IBP project. What must you enable for the S&OP operator which is specifically relevant for sub networks?
Please choose the correct answer.
Response:
A. Compute Expected Supply parameter
B. Normalize Quotas parameter
C. Node-Based isolation check
D. Balance Receipts parameter
正解:A
質問 8:
Your project requires end-to-end visibility and basic supply and demand planning. Which one of the following IBP Solution components do you recommend?
Please choose the correct answer.
Response:
A. Supply Chain Control Tower
IBP for Supply
B. IBP for Sales and Operations
IBP for Demand
C. Supply Chain Control Tower
IBP for Sales and Operations
D. Supply Chain Control Tower
IBP for Response
正解:C
浅见** -