Which risk response option 'takes the chance' that the risk will occur, with its full impact if it did?
A. Prepare contingent plans
B. Share the risk
C. Accept the risk
D. Transfer the risk
正解:C
質問 2:
Which is NOT described in the M_o_R risk management process guide?
A. Templates, their purpose and locations
B. Roles and responsibilities for the process
C. Procedures for escalation and delegation between the different perspectives
D. Tools and techniques to support the risk management process steps
正解:C
質問 3:
Which perspective is concerned with decisions about risks to long-term objectives that may not become apparent until well into the future?
A. Programme
B. Operational
C. Project
D. Strategic
正解:D
質問 4:
Which explains a use of the risk management policy in the identify context' step?
A. Describes how corporate governance will affect the risk management process
B. Identifies changes to the organization's market
C. Understand the maximum amount of risk that should be taken
D. Identifies how past events could become sources of risk
正解:C
質問 5:
Which of the M_o_R framework core concepts is informed by corporate governance principles and the international standard for risk management ISO31000:2009?
A. M_o_R principles
B. M_o_R process
C. M_o_R approach
D. Embedding and reviewing M_o_R
正解:A