A reduction in the lead time results from which of the following actions?
A. Increase in work-in-process, increase in throughput
B. Decrease in work-in-process, decrease in throughput
C. Decrease in work-in-process, increase in throughput
D. Increase in work-in-process, decrease in throughput
正解:C
質問 2:
Production activity control is essential to a closed-loop system because it:
A. lists the variety of products to be produced.
B. shows the complete production schedule.
C. measures actual output of products.
D. calculates resource requirements.
正解:C
質問 3:
Which of the following components are associated with inventory functions?
A. Transit, cycle, and warehousing
B. Transit, cycle, and safety stock
C. Raw, work in process (WIP), and finished goods
D. Safety stock, anticipation, and work in process (WIP)
正解:B
質問 4:
The actual output of a work center for a given time period can be determined by evaluating the:
A. number of standard hours in the queue.
B. number of standard hours per units produced.
C. number of machine hours.
D. amount of rated capacity less rework.
正解:B
質問 5:
Proper workplace organization calls for which of the following actions?
A. Increasing supervisor oversight
B. Placing all tools in a centrally located tool crib
C. Increasing the use of kanbans
D. Returning frequently used items to a nearby, fixed location
正解:D
質問 6:
Throughput for a family of parts can be increased by use of which of the following approaches?
A. Cell layout
B. Batch processing
C. Functional layout
D. High utilization
正解:A
質問 7:
Which of the following applications is an effective use of electronic data interchange?
A. Returned material authorization
B. Price increase
C. Routing
D. Advance shipment notice
正解:D
質問 8:
When a company moves from sampling inspection to internal process control, which of the following actions should be taken prior to evaluating supplier performance?
A. Conduct a supplier kaizen.
B. Establish target inventory levels.
C. Plan and analyze results.
D. Establish quality criteria.
正解:D
質問 9:
A work center has one machine that is operated for one shift per day. The shop runs an 8hour shift 5 days per week. Machine utilization has been 60% with efficiency at 80%. A routing through this work center has a standard run time of .10 hours per piece. Job number 1234 is for 200 pieces. If the utilization is improved to 80%, the difference in calculated lead time for the job is how many days?
A. 2.1
B. 1.3
C. 2.7
D. 1.0
正解:B
Fukawa -
実力をチェックできますから超安心で受験して受かるという最小限の対策で合格をめざす参考書だと思う。