Which statement describes the 'Implement' step within the recommended risk management procedure?
A. Assess the proximity of a risk
B. Implement the responsibilities for risks defined in the Risk Management Strategy
C. Identify the level of risks that can be tolerated by the project
D. Take planned action to respond to a risk
正解:D
質問 2:
Who are considered as the stakeholders in a project?
A. Only those who are users of the products
B. Everyone in the corporate organization
C. Only those benefitting the project
D. Everyone involved in or affected by the project
正解:D
質問 3:
Which describes a characteristic of a project?
A. It maintains business as usual profitability
B. It provides a quality service to customers
C. It involves a team with different skills
D. It enables established and proven best practices
正解:D
解説: (Pass4Test メンバーにのみ表示されます)
質問 4:
How does the project plan help to support the 'manage by stages' principle?
A. By defining products to ensure they are fit for purpose
B. By estimating the timescales and costs of the project
C. By identifying the major control points and milestones
D. By identifying the customer's quality expectations
正解:C
解説: (Pass4Test メンバーにのみ表示されます)
質問 5:
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
A. Both 1 and 2 are true
B. Neither 1 or 2 are true
C. Only 2 is true
D. Only 1 is true
正解:B
質問 6:
Which is an objective of the 'directing a project' process?
A. To give authority to deliver the project product
B. To select and appoint the project manager
C. To design the project management team roles
D. To create the plan to deliver the project product
正解:B
質問 7:
What is the result of the change derived from using the project's product?
A. Dis-benefit
B. Outcome
C. Benefit
D. Output
正解:B
質問 8:
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
A. Project Support
B. the risk owner
C. Project Assurance
D. the risk actionee
正解:D