Identify the missing word in the following sentence. Applying the 'aligns with objectives'
principle at the [ ? ] perspective ensures risk management is responsive to changes to objectives that meet shareholder needs, reputation and demand for services.
A. project
B. programme
C. operational
D. strategic
正解:D
質問 2:
Which is recorded in the risk response plan during the 'plan' step?
A. Unmanaged risks
B. Number of risks in different categories
C. Actions developed to mitigate threats
D. Actions to improve risk management
正解:C
質問 3:
Which is a responsibility of the team?
A. Develop the risk improvement plan
B. Run risk management workshops
C. Identify and escalate risks
D. Ensure adequate resources are available to implement the risk management strategy
正解:C
質問 4:
What is an opportunity?
A. An uncertain event that could have a negative impact on objectives or benefits
B. An uncertain event that could have a favourable impact on objectives or benefits
C. An event that has occurred resulting in a favourable impact on objectives or benefits
D. An event that has occurred resulting in a negative impact on objectives or benefits
正解:B
質問 5:
Which activity is focused on when the 'aligns with objectives' principle is applied to the project perspective?
A. Delivering defined business change products within budget and on time
B. Developing plans to improve the overall efficiency of the organization
C. Maintaining the appropriate levels of service delivery to new and existing customers
D. Implementing business strategy to improve organizational performance
正解:A
質問 6:
What is defined as the level of risk exposure that, once exceeded, will trigger an escalation?
A. Risk appetite
B. Risk perception
C. Risk tolerance
D. Risk capacity
正解:C
質問 7:
Which role provides sponsorship to ensure that risk management is embraced within the organization?
A. Senior manager
B. Assurance
C. Risk specialist
D. Manager
正解:A