Which document is a narrative description of products or services to be delivered by the project?
A. Contract
B. Project charter
C. Project statement of work
D. Business case
正解:C
質問 2:
Risk Event Status is defined as _____ .
A. Both 1) the severity of the consequences, and 2)how likely the event is to occur with risk.
B. Risk Probability x Amount At Stake.
C. how likely the event is to occur with risk.
D. (Cost + Benefit + Business Risk) / Insurable Risk.
E. the severity of the consequences.
正解:B
質問 3:
Stakeholder analysis identifies what information and relates it to the purpose of the project?
A. Requirements, influence, and functional department
B. Interest, requirements, and functional role
C. Requirements, expectations, and influence
D. Interest, expectations, and influence
正解:D
質問 4:
Which of the following is a KEY output of the Verify Scope process?
A. Customer acceptance of project deliverables
B. A more complete scope management plan
C. Improved schedule estimates
D. An improved project management information system
正解:A
質問 5:
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
A. Fixed price or lump-sum
B. Cost-reimbursable
C. Time and material
D. Cost-plus-fixed-fee
正解:A
質問 6:
All the techniques described below can be used to keep a meeting focused except:
A. Rephrase unclear ideas presented by group members
B. Recall agenda items/purpose of meeting
C. Encourage pursuit of interesting new ideas
D. All are acceptable techniques
E. Summarize discussion periodically
正解:C
質問 7:
You are the project manager for a top-secret software project for an agency of the United States government. Your mission-should you choose to accept it-is to complete the project using internal resources. The reason is that finding contractors with top-secret clearances takes quite a bit of time, and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this?
A. Extinction
B. Starvation
C. Addition
D. Integration
正解:D