CORRECT TEXT
Fill in the blank with the appropriate term.
______ (also called contractor conferences, vendor conferences, and pre-bid conferences) are meetings with prospective sellers prior to preparation of a bid or proposal.
正解:
Bidder conferences
質問 2:
You work as a project manager for PassGuide Inc. Two of your team members are held in a conflict on a module of the project assigned to them. You have told them to work together to find a mutually beneficial solution. Which of the following conflict resolution techniques will your team members follow to achieve the solution?
A. Competition
B. Collaboration
C. Compromise
D. Avoidance
正解:B
質問 3:
Mark works as a project manager for PassGuide Inc. You have to monitor the status of the project and product scope. Which of the following processes will you use to accomplish the task?
A. Control Scope
B. Create WBS
C. Verify Scope
D. Define Scope
正解:B
質問 4:
Jane works as a project manager for PassGuide Inc. She is calculating the estimated activity durations for her project. She is using parameters such as duration, budget, size, weight, and complexity from a previous similar project as the basis for estimating the new project. Which of the following estimate activity duration techniques is she using in the project?
A. Analogous
B. Parametric
C. Expert judgment
D. Three-point
正解:A
質問 5:
You work as a project manager for PassGuide Inc. You want to standardize your department's personnel resources to facilitate planning and controlling of project work. Which of the following components of project management will help you accomplish the task?
A. Gantt chart
B. Project network diagram
C. RBS
D. WBS
正解:C
質問 6:
Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impact for her project.
She and the stakeholder agree that the project management plan should be changed to eliminate the risk threat entirely. What risk response has Holly used in this instance?
A. This is the avoidance risk response.
B. This is the transference risk response.
C. This is the risk mitigation response.
D. This is a scope change and not a risk response.
正解:A
質問 7:
You are the project manager of TRT project. During execution phase of your project, Rick, a team member, complains that other team members are isolating him and this isolation is bothering him.
Which of the following is not a recommended step in order to resolve the issue?
A. Get more feed back from Rick.
B. Apply team building measures to improve the team's effectiveness.
C. Get feedback on Rick from other team members.
D. Shift Rick to another project.
正解:D