What is the goal of the 'assess - estimate' step?
A. Identify the threats and opportunities facing the organizational activity
B. Determine the risks with the greatest effect on an activities objectives
C. Assess the effectiveness of the risk management processes within an organization
D. Estimate and agree the budget required to manage risks to the activity
正解:B
質問 2:
What principle promotes dialogue with affected parties in a timely manner to help achieve organizational objectives?
A. Engages stakeholders
B. Achieves measurable value
C. Fits the context
D. Aligns with objectives
正解:A
質問 3:
Which is recorded in the'risk register'?
A. Organizational risk appetite and capacity
B. Risk management practices within an organization
C. Events that have already occurred
D. Threats and opportunities
正解:D
質問 4:
Which is a benefit of effective risk management?
A. Guarantees business benefits will be delivered
B. Eliminates risk-taking within an organization
C. Successful completion of all change activities
D. Organizations are better prepared to recover from unplanned incidents
正解:D
質問 5:
Which is NOT a recommended risk response option for an 'opportunity'?
A. Reduce
B. Enhance
C. Share
D. Transfer
正解:A
質問 6:
Which is NOT an action needed to achieve the goal of the 'assess - evaluate' step?
A. Determine which risks are independent of other risks
B. Determine which other risks will occur if a risk occurs
C. Evaluate the effectiveness of risk management across the organization
D. Calculate the total risk exposure for the activity
正解:C
質問 7:
Which BEST describes an area of uncertainty at the operational perspective?
A. Minimizing disruptions to customer services during transformational change
B. Availability of skills required to deliver services to customers
C. Variation to the schedule of a defined business product
D. Damage to the organization's infrastructure
正解:B