You are considering involving users during test execution. In general, what is the main reason for involving users during test execution? 1 credit
A. This can serve as a way to build their confidence in the system
B. They have good testing skills
C. They have the ability to also focus on invalid test cases
D. They are a cheap resource
正解:A
質問 2:
Continuing with the Scenario described in the previous question, which of the following topics would you need to address in detail in the master test plan? 3 credits
A. A logical collection of test cases
B. A description of dependencies between test cases
C. A list of boundary values for "advance amount"
D. An approach to regression testing
正解:D
質問 3:
IEEE 1028 also defines "management review" as a type of review. What is the main purpose of a management review? 1 credit
A. To monitor progress, assess the status of a project, and make decisions about future actions
B. Provide independent evaluation of compliance to processes, regulations, standards etc.
C. Establish a common understanding of requirements
D. Align technical concepts during the design phase
正解:A
質問 4:
As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria? 1 credit
A. Exit criteria are used to decide on when to stop testing.
B. The expectation is that development testing is not adequate.
C. Entry and exit criteria are a principal way for getting adequate resources.
D. Using entry and exit criteria will prevent software that is not or poorly tested from going to the next test level.
正解:C
質問 5:
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design. 2 credits
A. Response time
B. Usability
C. Valid and invalid advances
D. Language localization
E. All supported credit cards
正解:C,E
質問 6:
Which of the following would you expect to see in the master test plan? 1 credit
A. A list of the names of the testers who will carry out the performance testing for the final iteration.
B. A description of how the test cases are cross-referenced to requirements in the test management tool.
C. The test approach that will be applied at system integration testing.
D. A detailed identification of the resources that will carry out structural testing in the first iteration.
正解:C