A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What information is needed to develop a Class 2 definitive estimate?
A. Preliminary quantities with labor, material, and factors applied, square footage of facilities, minimum contingency detailed indirect costs
B. Square footage of facilities, factored indirects and home office costs
C. Vendor quotes, home office detailed estimate, preliminary quantities with labor, material, and factors applied
D. Soil data, detailed construction drawings, quantity takeoffs, minimum contingency detailed indirect costs, detailed engineering estimates
正解:D
質問 2:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
In Rensis1 4 model system, the exploitative-authoritative management style is one in which:
A. Informal organizations generally support the goals of the formal organization
B. Management issues orders, but employees have some freedom to comment
C. Management makes most decisions and passes them down
D. Management has a lot of confidence in the employees
正解:C
質問 3:
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
According to Maslow's hierarchy of needs, which level should be satisfied first?
A. Self-actualization
B. Physiological
C. Safety needs
D. Ego-status
正解:B
質問 4:
____________is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts.
A. Earned value
B. Forecast
C. Percent complete
D. Cost to complete
正解:C
質問 5:
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
What is the range of unit costs?
A. $48.22
B. $26.65
C. $485.00
D. $21.57
正解:C
質問 6:
Two of the most important things to know when planning a speech or lecture are the ______________and______________ of your audience.
A. Culture, understanding
B. Background, attitude
C. Political preference, sense of humor
D. Motivation, professionalism
正解:A
質問 7:
The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, the final price for the piece of equipment will be:
A. $375,658
B. $370,710
C. $378,750
D. $328,810
正解:A
質問 8:
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?
A. 10,526
B. 14,201
C. 16,215
D. 12,000
正解:A
桜井** -
優秀なCCP問題集です!合格になりました!友達もCCP問題集を勉強しています。