When is a bubble in the Investment Map displayed in gray?
A. when the bubble size parameter is not defined in the settings portlet for the project
B. when all health indicators are near the red limit
C. when the project does not have a value defined for the bubble size parameter
D. when no health indicators are defined
正解:C
質問 2:
Which statement is true about timesheet entry?
A. Timesheet entry is required for all participants affected to the project.
B. Timesheet entry is required for all projects/tasks.
C. Timesheet entry is allowed only for duration based projects/tasks.
D. Timesheet entry is allowed only for effort based projects/tasks.
正解:D
質問 3:
RPM provides the ability to search and assign resources to projects. At a minimum, what is required to accomplish this?
A. The resource pool must be "published."
B. The Project Manager attempting to assign from a particular pool must also be the Pool Manager.
C. The Project Manager must be a resource pool member to assign from that pool.
D. The Resource Manager must be assigned to the project.
正解:A
質問 4:
What happens when a new scope element is created and this element type has an associated default workflow?
A. Only the default workflow is available to be started.
B. The default workflow process starts automatically and no other workflow can be started for this element.
C. The default workflow process starts automatically.
D. If the user does not have security permissions to start a workflow, an error message appears.
正解:C
質問 5:
Which file formats can be used to export information from reports, pivot tables and charts (graphs)?
A. text (comma separated values), pictures (JPEG, WMF and BMP), HTML and PDF
B. text (fixed column width), pictures (JPEG, GIF and BMP), HTML and PDF
C. text (fixed column width), pictures (JPEG, WMF and BMP) and PDF
D. text (comma separated values), pictures (JPEG and GIF) and PDF
正解:A