Where can you define the valid receivers for production order costs?
A. In the production scheduling profile
B. In the valuation variant
C. In the settlement profile
D. In the costing variant
正解:C
質問 2:
What sequence do you follow in master data maintenance to define the production of a material?
A. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing
B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing
C. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
D. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
正解:B
質問 3:
After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials).
Which of the following planning file entries for this material are set by the system?
A. The BOM explosion, the NETCH, and the NETPL planning indicators
B. The NETCH and NETPL planning indicators
C. The BOM explosion and the NETPL planning indicator
D. The BOM explosion indicator
正解:A
質問 4:
What functions can you use for suboperations?(Choose two)
A. Costing
B. Production/Resource tools allocation
C. Material component allocation
D. Capacity planning
正解:A,D
質問 5:
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define?(Choose two)
A. Handling existing procurement proposals outside the planning time fence.
B. Handling new requirements within the planning time fence.
C. Handling existing procurement proposals within a planning time fence.
D. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.
正解:C,D
質問 6:
Which activities lead to a reduction of the capacity requirements for an operation?(Choose
three)
A. Confirming the operation
B. Posting the goods receipt for the production order
C. Reducing the order quantity
D. Setting the status technically complete (TECO)
E. Rescheduling the operation
正解:A,C,D
質問 7:
You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.
What do you have to consider in this scenario?
A. Planned orders are created within the planning time fence and automatically firmed by requirements planning.
B. Planned orders that are created by requirements planning are shifted to the end of the planning time fence.
C. Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
D. The MRP controller cannot create planned orders within the planning time fence.
正解:B